Planned Activity Project Erebus Floating Offshore Wind Farm - Notice to Mariners Update: Please...
Notice to Mariners
This page displays all BGW’s Notice to Mariners, current and historic
25/04/2023 – NtM Erebus/002 V003 Offshore Geotechnical Survey Update
Planned Activity Project Erebus Floating Offshore Wind Farm - Notice to Mariners Erebus...
19/04/2023 – Erebus NtM 002 v02 – Nearshore Geotech Survey
Planned Activity Project Erebus Floating Offshore Wind Farm - Notice to Mariners Due to weather...
28/03/2023 – Erebus NtM 002 v01 – Nearshore Geotech Survey
Planned Activity Project Erebus Floating Offshore Wind Farm - Notice to Mariners A geotechnical...
03/03/2023 – Geophysical Unexploded Ordnance (UXO) Survey
Planned Activity Project Erebus Floating Offshore Wind Farm - Notice to Mariners Erebus Floating...
08/12/2022 – Floating LiDAR Equipment Planned Service Visit
Planned Activity Floating LiDAR Equipment Planned Service Visit To inform the engineering designs...
10/05/2022 – Floating LiDAR Redeployment
Redeployment and Operation Floating LiDAR System To inform the engineering designs and...
03/05/2022 – Redeployment of Floating LiDAR
Redeployment of the Floating LiDAR system following recovery in January 2022 was expected to take...
20/04/2022 – Redeployment of Floating LiDAR
The recovery of the capsized Floating LiDAR System (including the mooring and clump weight),...
20/01/2022 – Recovery of Moorings
Recovery of Moorings An attempt to recover two moorings, estimated to be located within the...