Planned Activity

 

Maintenance to the floating LiDAR, located at the location listed below, will take place between the 19/06/2021 and 23/06/2021.
There are currently 3 scenarios for the maintenance operation. Which scenario is undertaken is based on the weather/sea conditions at the time of operation:
Plan A: Maintenance work would be fully conducted offshore at the location listed below.
Plan B: The floating LiDAR will be bought on board the vessel to sail to harbour (Milford) to complete the works. Full mooring and clump weight would be recovered for this. The floating LiDAR would then be redeployed at the location listed below.
Plan C: The floating LiDAR will be towed to harbour (Milford) to complete the works. Mooring and clump weight would be fully recovered. The floating LiDAR would then be redeployed at the location listed below.
The floating LiDAR has the following identifiable features:
– Yellow in colour
– FI (5) Y 20s light (5 nm range)
– Yellow ‘X’ shaped topmark
– Flash rate not exceeding 30 per minute

 

For further details click on the button below: